You are looking at the transformer frame and XO to ground connection. This is a 277/480-120/208 3ph customer owned 225 Kva pad mounted transformer that is fed from a separate service. It is located outside on a concrete pad where it serves a large MDP in the same fenced in area. Since this is not inside a building it does not connect to building steel but instead connects to earth and the structural steel of the pad and fencing that encloses it.
With all of that being said, was the electrician required to mark this ground with green tape?