If you had a 480/277v to 208/120v wye-type transformer where the primary side of the transformer (xfmr) was fed from an MDP after the service, what table would you use to size the supply-side bonding jumper on the secondary side of the transformer if the xfmr was supplying power to a panelboard for an office?
Remember that the primary side feeding the transformer from the MDP would be sized per Table 250.122 as it is an equipment grounding conductor.
Remember that the primary side feeding the transformer from the MDP would be sized per Table 250.122 as it is an equipment grounding conductor.