In this old photo of mine, you can see that a single piece of rigid conduit along with unistrut was used to support 3 other vertical pieces of RMC. So, one piece of rigid is being used to support 3 other pieces of rigid and the shut off enclosure to the 4 pieces of unistrut.
Is this a violation since the conduit being used for support is not conduit being used as an active conduit?
If you think so, please cite the NEC code section.

Is this a violation since the conduit being used for support is not conduit being used as an active conduit?
If you think so, please cite the NEC code section.