• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

nec 250

  1. jar546

    Compliant with NEC 250.24(A)(1)

    As you can see by this photograph, the grounding electrode conductor (GEC) for this service comes into the top of the panel on the meter-base side and connects to a lug that is mechanically connected to a factory installed strip of metal that then connects the ground lug where the service...
  2. jar546

    Problem with Concrete Encased Electrode

    Can you tell me if this is a violation of the NEC IF the contractor chooses to bond to the rebar only and does not use ground rods? If so, what section?
Top