• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

Bottled water plant?

steveray

SAWHORSE
Joined
Nov 25, 2009
Messages
11,751
Location
West of the river CT
Has anyone ever done one? I might be getting one and supposedly they do everything from make the bottles to purify the water to bottle and ship.....I have a pre-pre-preconstruction meeting with them on the 27th....My main unknown concern is the bottle making process. 300,000+ sqft building.
 
Bottle making process should be F-1 assuming they are getting shipments of the PET beads and then melting them to blow the bottles.
 
Frank said:
Bottle making process should be F-1 assuming they are getting shipments of the PET beads and then melting them to blow the bottles.
Yep, I am assuming F1 S1 B mixed use non separated....Unlimited area single story IIB construction....I don't know what they will have for me for info, but I want to bring up as many concerns as I can early to minimize plan review issues...They are saying they have a really aggresive timeline (Like they want to be in this year, and they have no approvals of any type so far...)
 
steveray said:
Yes Sir......Certainly going to ask for all of their plastic info, (type, amount, how stored, and the process)
NO Tech Report as in FPE reviews the entire business and makes recommendations, such as commodity type, storage there of, fire sprinkler desing, chemical storage needs ETC !!!!!!!!!!!!!!!
 
steveray said:
State law requires FPE design....I require it to be complete or thorough...
I was kind of thinking an overview/detailed review of the project.

If you want to use thier FPE or require an approved third party. Not just design but details of all processes, storage, chemicals and code anyalsis how to protect the place.

104.7.2 Technical assistance. To determine the acceptability

of technologies, processes, products, facilities, materials

and uses attending the design, operation or use of a building

or premises subject to inspection by the fire code official, the

fire code official is authorized to require the owner or agent

to provide, without charge to the jurisdiction, a technical

opinion and report. The opinion and report shall be prepared

by a qualified engineer, specialist, laboratory or fire safety

specialty organization acceptable to the fire code official

and shall analyze the fire safety properties of the design, operation

or use of the building or premises and the facilities

and appurtenances situated thereon, to recommend necessary

changes. The fire code official is authorized to require

design submittals to be prepared by, and bear the stamp of, a

registered design professional.
 
I have done a couple of bottle manufacturers here. Generally F1, S1, B. Unless they are making the beads then a whole different story.
 
Top