We require the power to be on for the final inspection. We do a temporary final electrical inspection where the house is buttoned up, all outlets, lights, switches, garbage disposal, dishwasher etc.... We spot check various items, outlets, switches etc to verify wiring...... Also on the temp electrical final we require the face of the panel to be removed so we can verify installation. Once we've determined all is well we okay the power to be turned on.
Then when we do the CO we verify everything works properly...water heater, sd's, afci's, gfci's, ac, heat etc.