• Welcome to The Building Code Forum

    Your premier resource for building code knowledge.

    This forum remains free to the public thanks to the generous support of our Sawhorse Members and Corporate Sponsors. Their contributions help keep this community thriving and accessible.

    Want enhanced access to expert discussions and exclusive features? Learn more about the benefits here.

    Ready to upgrade? Log in and upgrade now.

NEC 555 Docks, Marinas, Boatyards & GFP

jar546

CBO
Joined
Oct 16, 2009
Messages
13,001
Location
Not where I really want to be
I inspected a new system the other day that used ground fault sensing via CT "donuts" on the dock pedestal feeders connected to a shunt trip breaker at the MDP. Where installed, the CT controllers did not have any visible settings on them to show that they were the required maximum 100ma per the NEC 555. The contractor did not know and none of the literature had this information, therefore I was unable to pass the inspection. They had to either remove the controller module or show me a spare which they did on a reinspection. I think the manufacturer should have this information where it is visible once installed. Here are some pics.
IMG_6599.JPG

As seen during inspection