Okay so you are in Westchester County, I just wanted to be sure you weren't in the five boroughs of NYC as its a different set of codes there.Project is in Eastchester, NY
Okay so you are in Westchester County, I just wanted to be sure you weren't in the five boroughs of NYC as its a different set of codes there.Project is in Eastchester, NY
My personal opinion is its one and the same in the end. I think this comes down to semantics and good luck with that.Work area is defined as "....portions of a building consisting of all reconfigured spaces"
I was trying to determine what part of my work was considered a reconfigured space and thus included in the work area.
Important here because if my work area was more than 50% of floor area I need sprinklers.
So, I accept the "if its a level 2 alt then its part of work area"
But the inspector made me include areas where I am just replacing finishes (which is level 1 type work)
Work area is defined as "....portions of a building consisting of all reconfigured spaces"
I was trying to determine what part of my work was considered a reconfigured space and thus included in the work area.
Important here because if my work area was more than 50% of floor area I need sprinklers.
So, I accept the "if its a level 2 alt then its part of work area"
But the inspector made me include areas where I am just replacing finishes (which is level 1 type work)